Alluri Sitarama Raju International Airport Construction Work in Bhogapuram : విజయనగరం జిల్లా భోగాపురంలో అల్లూరి సీతారామరాజు అంతర్జాతీయ విమానాశ్రయం నిర్మాణ పనులు వాయువేగంతో సాగుతున్నాయి. గడువు కంటే ముందే లక్ష్యాన్ని చేరుకునేందుకు గుత్తేదారు సంస్థ పనులను పరుగులు పెట్టిస్తోంది. సీఎం చంద్రబాబు ఆదేశాలతో పనుల పురోగతిపై ఎప్పటికప్పుడు ప్రత్యేక దృష్టి సారిస్తున్న కేంద్ర పౌర విమానాయాన శాఖ మంత్రి రామ్మోహన్ నాయుడు నేడు మరోసారి అధికారులతో సమావేశం కానున్నారు.
Category
🗞
NewsTranscript
00:00It is time to fulfil the dream of the people of Uttar Andhra Pradesh.
00:05The 4,592-square-foot Bhogapuram Alluri Seetha Ramaraju International Airport construction is in full swing.
00:13The construction of the first floor was completed on June 1, 2026.
00:17The construction of the first floor was completed on June 1, 2026.
00:21The construction of the first floor was completed on June 1, 2026.
00:27Two 3.8-kilometre-long runways are being built here to facilitate the landing of heavy aircrafts.
00:34The construction work is being carried out by the Central Minister, Ram Mohan Naidu.
00:40The construction work is being carried out by the Central Minister, Ram Mohan Naidu.
00:51In the 16 months since the construction of the airport began, 68% of the work has been completed.
00:56The Central Minister, Ram Mohan Naidu, followed the Central Government officials to Bhogapuram.
01:03The Central Minister, Ram Mohan Naidu, followed the Central Government officials to Bhogapuram.
01:08The work has been carried out by the people's representatives, officials and the construction organization representatives.
01:14In the last ICP review, the project was completed with 31.8% of the work.
01:19In the last ICP review, the project was completed with 31.8% of the work.
01:24As per the GMR System's goal of every month, 53.48% of work should have been completed by the end of the last month.
01:3214.44% of the work has been completed.
01:35The connection building work has been completed with 41.78%.
01:39The terminal building work was completed with 55.64%.
01:42Air traffic control work has completed with 64.22%.
01:44The taxiways have completed with 84.85%.
01:47The runway work has been completed with 95.08%.
01:50The land work has been completed with 100%.
01:54The CMRDA has decided to expand the 15 roads that have been identified as unconnected to the airport and increase connectivity.
02:01If these are turned into four-lane roads, it will be easier to reach Bhogapuram Airport.
02:08The government feels that if these roads are completed, the passengers will not have traffic problems for two years.
02:24For more information, visit www.cmrda.gov