Category
🗞
NewsTranscript
00:00 This year we have rebuilt the heat network of the last section at Kazimierz Wielki street.
00:07 It is from Świętego Mikołaja street to Wierzbowa street.
00:11 We have rebuilt 1140 meters of the channel heat network from the 60s.
00:18 We have built a new heat network in a pre-insulated system, with an alarm system.
00:27 So in the future we will be able to measure any leaks and breakdowns in a few dozen centimeters.
00:37 However, we do not expect it to be faster than in a dozen or so years.
00:42 There are currently 115 buildings connected to this network.
00:47 There are hotels, restaurants, residential buildings.
00:51 So it is quite a large number in this area.
00:57 We do not expect that there will be any breakdowns or longer breaks in heat supply in the next few years.
01:04 We are talking about the replacement of a network that was already 60-70 years old.
01:09 There were situations where breakdowns appeared and the network had to be replaced.
01:16 The second big task we did in Wrocław this year was to rebuild the heat network at Krakowska Opolska street.
01:25 This is a master network from the power plant in Siechnica.
01:31 There, in total, about 2.5 km of the DN 800 heat network was rebuilt.
01:39 The channel network was also replaced.
01:46 It was a mixture of bitumen and cork that insulated the old channel network.
01:53 However, there were breakdowns in recent years, because it was also a network from the 60s, 70s, so it was already an age-old network.
02:02 This year, we completed the second stage, which included replacing about 1,400 m of the DN 800 network.
02:10 It was actually completed in a few days, because the energy readiness was achieved at the end of September.
02:18 However, the reconstruction work was still ongoing and ended relatively recently.
02:25 you