• last year
Relacja z budowy nowego kampusu AM w Bydgoszczy. Inwestycja warta blisko 400 mln zł ma być ukończona w 2025 roku. Nowy kompleks akademii powstaje nad glinianką między ulicami Kamienną i Chodkiewicza

Category

🗞
News
Transcript
00:00 We are currently on the third floor of the building, which will have 7 technical floors, plus 2 underground floors, minus 2 is the garage, minus 1 is the concert hall with the stage and wardrobe of the performers.
00:26 The building has a surface area of about 8,000 square meters. We took about 2,000 square meters, entering its outline.
00:37 Therefore, we had to install the Larsen tight walls to isolate from the water, and then we had to make the wall gaps around the entire building. This technology is generally adopted for buildings that have underground conditioning.
00:57 Therefore, we had to dig 9.5 square meters deep to install the foundations, so it is impossible to secure the excavation trenches at such a depth. Therefore, the concrete walls, which are at the same time the walls of the building, are at the same time the board and the scaffolding for the excavation.
01:20 This is the building of the Music Academy campus, which will focus all the functions that the Academy has so far in several buildings scattered throughout Bydgoszcz.
01:35 There will be 4 concert halls here, from the chamber hall through the symphonic hall, the opera and organ halls. The assumptions were that when designing it, it should be passive, but with the exception of the tightness of the building and the isolation of the building.
02:00 We are not able to satisfy the needs of this building 100%. The OZE solutions were used, for example, by using photovoltaics, a heat pump for which there will be 106 fans per 100 meters, and ventilation with recovery.
02:21 That's the only.
02:21 (dramatic music)

Recommended